Question: These are all True or False questions for question 1: -When activity duration are stochastic, the expected duration of a path is equal to the
These are all True or False questions for question 1:
-When activity duration are stochastic, the expected duration of a path is equal to the sum of the expected times of the activities on that path.
-Activities on a AON (Activity on Node) network that have a slack value greater than zero are critical activities.
-Project manager is ultimately responsible for the success or failure of the project and must effectively manage the work, human resources, communications, quality, time and project costs.
-Work breakdown structure (WBS) is a hierarchical listing of what must be done during a project.
-In following strategy, we build capacity when demand exceeds current capacity.
-Bottleneck is an operation in a sequence of operations whose capacity is lower than that of the other operations.
Please answer any you can!! Thank you!