Question: these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: Production plans for complete kits

these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information:
Production plans for complete kits are as follows:
Start assembling 11,000 kits in week 2
Start assembling 15,500 kits in weeks 3,4, and 5
Start assembling 18,000 kits in week 6
The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements.
All scheduled receipts, lead times, and beginning inventory levels are shown.
Click the icon to view the MRP records.
Construct the material requirements plan for item System unit (enter your responses as whole numbers).
CD-ROM drivers: Lead Time =1 week; Minimum order quantity =9,000
Gross requirements
Scheduled receipts
Projected ending inventory: 16,000
Net requirements
Planned receipts
Planned orders
There are three tables need to be filled in. The first one is the first photo. The second and third tables are in the second photo. Thank you!
 these items are level 1 items that make the level 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!