Question: This assignment was locked Oct 25 at 11:59pm. CHAPTER 9 TECHNICAL CASE #9 INFORMATION Kaz's Computing Conglomerate wants to build a new computer assembly line
This assignment was locked Oct 25 at 11:59pm.
CHAPTER 9 TECHNICAL CASE #9
INFORMATION
Kaz's Computing Conglomerate wants to build a new computer assembly line for a new product called the Reverse Notation Assembly (RNA). Tasks, times and order of processing/immediate predecessors is noted below:
|
TASK | ASSEMBLY TIME AT THIS TASK (in seconds) | IMMEDIATE PREDECESSORS: TASK MUST FOLLOW THE TASK LISTED HERE |
| A | 12 |
|
| B | 15 | A |
| C | 8 | A |
| D | 5 | B, C |
| E | 20 | D |
| Time for Task OR Total Task Time
| ? |
|
Kaz's goal = produce 180 RNA's per hour.
QUESTIONS (should you decide to accept them - which you must to obtain 5 points):
- BALANCE THE ASSEMBLY LINE: DRAW A PRECEDENCE DIAGRAM FOR THIS PROCESS (BE SURE TO INCLUDE THIS CHART AS WELL);
- CALCULATE YOUR CYCLE TIME
- CALCULATE YOUR THEORETICAL MINIMUM FOR THE NUMBER OF WORKSTATIONS IN KAZ'S PROCESS
- CAN THE THEORETICAL MINIMUM BE REACHED - IF YES, SHOW IT BY RECREATING THE PRECEDENCE DIAGRAM WITH EACH OF THE WORKSTATIONS OUTLINED.
FOR 1 EXTRA POINT - Tell me about this operations efficiency and idle time - what do these two numbers tell you about this operation?
HINT: Note the WORK DAY is expressed as ONE HOUR and make sure to convert everything to the same time element (hours, minutes or seconds).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts