Question: This chart is used to display the remaining work effort for the sprint. It shows the time period on the horizontal axis and the backlog

This chart is used to display the remaining work effort for the sprint. It shows the time period on the horizontal axis and the backlog items on the vertical axis. Team members update this chart at the end of each day.
a. Burn-down chart
b. Gantt chart
c. Run chart
d. RAM
This chart is used to display the remaining work