Question: This constraint represents Air Express' Monday minimum worker requirement. Why was a used versus an =? X 3 + X 4 + X 5
This constraint represents Air Express' Monday minimum worker requirement. Why was a "" used versus an "="?
X3 + X4 + X5 + X6 + X7 27
| The "=" will always produce an infeasible constraint. | ||
| The "" is needed to accommodate workers held over from Sunday. | ||
| The "" is less restrictive. | ||
| Solver only accepts "" constraints. |