Question: This evaluation applies for both the cost and schedule performance indices in Earned Value Management: 1.If the value is < 2, then the project is
This evaluation applies for both the cost and schedule performance indices in Earned Value Management:
1.If the value is < 2, then the project is behind schedule or over budget, if the value is > -2 then the project is ahead of schedule or under budget.
2. If the value is = 1, then the project is behind schedule or over budget, if the value is = 1 then the project is ahead of schedule or under budget.
3.If the value is < 1 the project is behind schedule or over budget, if the value is > 1 the project is ahead of schedule or under budget.
4.If the value is > 1, then the project is behind schedule or over budget, if the value is < 1 then the project is ahead of schedule or under budget.