Question: This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized
This example has level resources of three resources for eight days. If the project is limited to two resources, how should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks with the least slack have the lower number.
Flowchart depicting a project timeline with five sequential tasks, each requiring a specific number of workers and days to complete.
Question options:
Paths would be and
Paths would be and
Paths would be and
Path would be