Question: This highly formal document is written during the project planning phase and includes the project's schedule, budget, and assigned resources that are used by the
This highly formal document is written during the project planning phase and includes the project's schedule, budget, and assigned resources that are used by the project manager to guide the execution and control of the project. O Statement of Work O Scoring model O Project charter O Project plan