Question: This information is used for the first four questions where you will calculate materials and labor variances. Shelley Company bought 3,000 pounds of materials for

This information is used for the first four questions where you will calculate materials and labor variances. Shelley Company bought 3,000 pounds of materials for $3,750. They used 2,800 pounds to produce 1,450 units of output. Direct labor costs totaled $18,000 for 600 hours of work. Standards have been set as follows: Direct Materials: 2 pounds @ $1.10 per pound .5 hours @ $32 per hour Direct Labor The materials quantity variance is: $880 unfavorable $ 420 favorable $110 unfavorable $110 favorable $880 favorable