Question: This information is used for the first four questions where you will caleolate naterials and labor variances. Shelley Company bought 3,000 pounds of materials for
This information is used for the first four questions where you will caleolate naterials and labor variances. Shelley Company bought 3,000 pounds of materials for $3,750. They used 2,800 pounds to produce 1,450 units of output. Direct labor costo totaled $10,000 for 500 hours of work. Standards have been set as follows: Direct Material: pounds 51.10 per pound Direct Labor .5 hours 532 per hour The materiale price variances 5420 navorable 5610 favorable 450 favorable 5450 favorable 20 taverne