Question: This is a multiselect question, at least one answer is correct, but select ALL of the correct answers. Cost estimates that are based on real

This is a multiselect question, at least one answer is correct, but select ALL of the correct answers.
Cost estimates that are based on real numbers or figures after completion of prelimary design work are called parametric estimates
An order of magnitude estimate is used when there isn't a lot of information or time
Taking the design for a new house and comparing it to a previous design but adjusting it 3% because it's more complex, and then reducing it by 5% because it's a bit smaller is a analogous estimate.Question 5(1 point)
When working on a complex project, a PMBOK definitive estimate (-5+10) was
used to come up with the estimate of $770. What would be the dollar value of the
low end range of the estimate?
Your Answer:
Answer
 This is a multiselect question, at least one answer is correct,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!