Question: This is a multiselect question, at least one answer is correct, but select ALL of the correct answers. An example of Rules of Performance Measurement

This is a multiselect question, at least one answer is correct, but select ALL of the correct answers.

An example of Rules of Performance Measurement in Cost Mgmt Planing could be comparing the labour rates of workers assigned to your project

A Process Description in Cost Mgmt Planning could be the choice of the currency you will use for the project (eg Cdn $, Rupee, Ven, Euro)

An activity with a high level of Precision could be less accurate than an activity with a low level of Precision