Question: (This is a Project Management question) A few project members in your team work from India and they plan not to work for two days
(This is a Project Management question)
A few project members in your team work from India and they plan not to work for two days due to a national holiday. You as the project manager should:
a: Because this is a US project, they should follow US policies
b: ask them to return to work
c: respect their national holidays
d: ask them to work the weekend instead