Question: This is a Software Engineering Question regarding project managment. To simplify things I have posted the previous question below, so everyone can get an idea


This is a Software Engineering Question regarding project managment.
To simplify things I have posted the previous question below, so everyone can get an idea what we're dealing with.

d) Given the following risk severity matrix, where would you place each risk A, B, C D, E? (Round to the upper category when on a boundary.) Likelihood Impact Medium High $500K) Low (s$250K) High (-75%) Medium (25-7596) Low (