Question: This is all that was provided. Assume that activity G has the following times: Early start time = 7 days Early finish time = 13

This is all that was provided. Assume that
This is all that was provided.
Assume that activity G has the following times: Early start time = 7 days Early finish time = 13 days Late start time = 15 days Late finish time = 21 days Which of the following statements is true about activity G? Activity G is on the critical path. Activity G takes 13 days to complete. Activity G has a slack time of 15 days. Activity G is not on the critical path