Question: This is all the information given Below is the bill of material for a skate board. Indented BOM Skate Board Part Description Level Planning Factor
This is all the information given
Below is the bill of material for a skate board.
| Indented BOM Skate Board | ||
| Part Description | Level | Planning Factor |
| Board | 1 | 1 |
| Wheels | 1 | 4 |
| Axles | 1 | 2 |
| Hardware kit | 1 | 1 |
| Sticker set | 1 | 1 |
Skate Boards - Level 0
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Gross Requirements
100
150
75
0
200
200
Projected on-hand inventory=150
Net Requirements
Planned Order Releases
Q=100; LT=1; SS=0
Fill in the gross requirements based on the BOM and the planned order releases for Skate Boards.
Next calculate the projected on-hand inventory and the net requirements for axles. Finally, based on the order policy and lead time for axles, determine the Planned Order Releases for axles.
Below is the MRP report for Axles.
| Axles - Level 1 | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 |
| Gross Requirements | ||||||
| Projected on-hand inventory = 325 | ||||||
| Net Requirements | ||||||
| Planned Order Releases | ||||||
| Q=100; LT=1; SS=0 |
Answer the following questions based on the values you calculated in the table above.
What is the pattern of gross requirements for axles in the prompt above from left to right over the course of the 6 weeks?
Group of answer choices
200, 200, 0, 400, 400, 0
100, 100, 0, 200, 200, 0
200, 0, 50, 50, 100, 0
50, 50, 0, 100, 100, 0
What is the pattern of on-hand inventory for axles in the prompt above from left to right over the course of the 6 weeks?
Group of answer choices
125, 25, 25, 25, 25, 25
325, 125, 25, 25, 25, 25
200, 150, 75, 75, 50, 50
100, 0, 200, 200, 0, 50
Fill in the gross requirements based on the BOM and the planned order releases for Skate Boards.
Next calculate the projected on-hand inventory and the net requirements for wheels. Finally, based on the order policy and lead time for wheels, determine the Planned Order Releases for wheels.
Below is the MRP report for Wheels.
| Wheels - Level 1 | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | |
| Gross Requirements | |||||||
| Projected on-hand inventory=500 | |||||||
| Net Requirements | |||||||
| Planned Order Releases | |||||||
| Q=100; LT=1; SS=0 |
Answer the following questions based on the values you calculated in the table above.
Based on the prompt above, the gross requirements for wheels in Week 4 are 400.
Group of answer choices
True
False
Based on the prompt above, the only week which projected on-hand inventory for wheels is not 0 is in week 2.
Group of answer choices
True
False
Based on the prompt above, the net requirements for wheels in Week 5 are 800.
Group of answer choices
True
False
Based on the prompt above, the planned order releases for wheels in Week 3 are 600.
Group of answer choices
True
False
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts