Question: This is all the information that was given to me in the homework thank you for the help. 2.) Please use this information for the
This is all the information that was given to me in the homework thank you for the help.
2.) Please use this information for the next few questions:
Which activity would be the best activity to start with when determining early start and early finish times?
Group of answer choices
a.) Activity A
b.) Activity F
c.) Activity J
3.)
Using the info from above, which activity would be best to start with when determining late start and late finish times?
Group of answer choices
a.) Activity A
b.) Activity F
c.) Activity J
4.)
Now we're looking to lower our project completion time by crashing. Based on the information above and what we learned in class, what is the total cost to reduce the original project completion time by 3 weeks?
Group of answer choices
a.) $1,530
b.) $2,510
c.) $3,550
d.) $4,150
Description Activity | Duration Crash (weeks) | Time (weeks) Preceding Activity(ies) Crashing Cost/Week Determine gala theme Reserve portal location for gala 5 $900 $1,020 $980 $1,500 $630 Create Marketing Plan Ray Parker, Jr. to audition musical acts Determine ticket sales method Purchase supplies, including Stay Puff marshmallows Pick musical act and sign contract Sell tickets in person Sell tickets online $700 $550 $690 $1,150 Gala! H, I, F, GStep by Step Solution