Question: This is an academic assignment. The problem statement is as follows: In the aftermath of September 11, 2001, terrorist attacks on the World Trade Center,
This is an academic assignment.
The problem statement is as follows:
In the aftermath of September 11, 2001, terrorist attacks on the World Trade Center, the New York City Department of Design and Construction was put in charge of recovery and clean-up operations at the site. The attack killed 2,823 people, destroyed a total of 8 buildings, and crushed 1,300 feet of the subway tunnel. Ultimately, the clean-up operations involved four construction firms, 3,000 workers, and 3.1 million man-hours. It took more than 100,000 truckloads to carry the 1.8 million tons of debris from the site. Amazingly, no workers were killed or critically injured during the clean-up effort, which officially ended on May 30, 2002, at a cost of $650 million. (Source: www.pbs.org/americarebuilds) Obviously, a project of this magnitude could not be completed successfully without careful planning and coordination of many, many activities. Indeed, many clean-up activities could be considered subprojects of the entire clean-up operation. Imagine that you were the person in charge of the clean-up operations at the World Trade Center site. No one has ever faced this task before, so no one can give you a nice, neat list of things to do with precise time estimates for each activity. It is an enormous task requiring careful consideration of human emotion, dignity, and safety concerns in addition to the monumental logistics and financial issues. And the world is watching all you do.
The demands of the issue are as follows:
Identify the key top-level activities you think would go into the clean-up project and prepare an AON project network summarizing the precedence relations among these activities. Also, describe how you would go about estimating the activity times and financial costs associated with these activities.
Note: I just want to estimate the amount of activities. Figures in millions of dollars
| S.No | Detailed Activities | Estimated Financials |
| 1 | Secure the parameter | |
| 2 | Engage all the Stakeholders | |
| 3 | Setup quick response emergency team | |
| 4 | setup team for clean up activities | |
| 5 | Appoint a person to address media queries | |
| 6 | Setup a backup emergency team to be present at the site 24x7 | |
| 7 | Restore electricity, water supply and drainage system of the affected area | |
| 8 | Setup a temporary office on site | |
| 9 | Get access to the blueprint of the buildings and the subway | |
| 10 | Inspection of affected areas | |
| 11 | Split the affected areas into sector/grids | |
| 12 | Identify alternate public traffic routes | |
| 13 | Identify the pathways for emergency services | |
| 14 | Identify routes for debris collection | |
| 15 | Identify the landfill and recycling facilities | |
| 16 | Identify temporary dumping grounds | |
| 17 | set-up communication towers | |
| 18 | Utilize identified traffic routes for public transportation | |
| 19 | Utilize identified routes for debris and waste transportation | |
| 20 | Air surviellance and Monitoring | |
| 21 | Liase with construction and transport companies | |
| 22 | Estimate the number of resources required | |
| 23 | Estimate the budget and timeline needed to complete the tasks | |
| 24 | Get required approvals | |
| 25 | Hire site workers | |
| 26 | Appoint supervisors for each team | |
| 27 | Lease machineries, Vehicles and excavation equipments | |
| 28 | Deployment of labourers across site | |
| 29 | Breakdown debris into smaller pieces | |
| 30 | Response based clean up - save human lives | |
| 31 | Prioritize the cleaning on the basis of Population density, Schools, nursing, Environmental impact | |
| 32 | Segregate the waste into recyclable, non- recyclable, electronic waste and company assests | |
| 33 | Send Recyclable waste to identified recycling facilities | |
| 34 | Send non-recyclable waste to temporary dumping grounds | |
| 35 | Send electronic waste to elctronic recycling facilities | |
| 36 | Distribute assets to their respective firms | |
| 37 | Setup weekly meetings with the supervisors to discuss on the challenges | |
| 38 | Ensure the workers' fundamental requirements are met | |
| 39 | Handle Media and Public relations | |
| 40 | Provide daily status updates on the progress | |
| 41 | Finalize cleanup and restoration of the services |