Question: This is an academic assignment. The problem statement is as follows: In the aftermath of September 11, 2001, terrorist attacks on the World Trade Center,

This is an academic assignment.

The problem statement is as follows:

In the aftermath of September 11, 2001, terrorist attacks on the World Trade Center, the New York City Department of Design and Construction was put in charge of recovery and clean-up operations at the site. The attack killed 2,823 people, destroyed a total of 8 buildings, and crushed 1,300 feet of the subway tunnel. Ultimately, the clean-up operations involved four construction firms, 3,000 workers, and 3.1 million man-hours. It took more than 100,000 truckloads to carry the 1.8 million tons of debris from the site. Amazingly, no workers were killed or critically injured during the clean-up effort, which officially ended on May 30, 2002, at a cost of $650 million. (Source: www.pbs.org/americarebuilds) Obviously, a project of this magnitude could not be completed successfully without careful planning and coordination of many, many activities. Indeed, many clean-up activities could be considered subprojects of the entire clean-up operation. Imagine that you were the person in charge of the clean-up operations at the World Trade Center site. No one has ever faced this task before, so no one can give you a nice, neat list of things to do with precise time estimates for each activity. It is an enormous task requiring careful consideration of human emotion, dignity, and safety concerns in addition to the monumental logistics and financial issues. And the world is watching all you do.

The demands of the issue are as follows:

Identify the key top-level activities you think would go into the clean-up project and prepare an AON project network summarizing the precedence relations among these activities. Also, describe how you would go about estimating the activity times and financial costs associated with these activities.

Note: I just want to estimate the amount of activities. Figures in millions of dollars

S.No Detailed Activities Estimated Financials
1 Secure the parameter
2 Engage all the Stakeholders
3 Setup quick response emergency team
4 setup team for clean up activities
5 Appoint a person to address media queries
6 Setup a backup emergency team to be present at the site 24x7
7 Restore electricity, water supply and drainage system of the affected area
8 Setup a temporary office on site
9 Get access to the blueprint of the buildings and the subway
10 Inspection of affected areas
11 Split the affected areas into sector/grids
12 Identify alternate public traffic routes
13 Identify the pathways for emergency services
14 Identify routes for debris collection
15 Identify the landfill and recycling facilities
16 Identify temporary dumping grounds
17 set-up communication towers
18 Utilize identified traffic routes for public transportation
19 Utilize identified routes for debris and waste transportation
20 Air surviellance and Monitoring
21 Liase with construction and transport companies
22 Estimate the number of resources required
23 Estimate the budget and timeline needed to complete the tasks
24 Get required approvals
25 Hire site workers
26 Appoint supervisors for each team
27 Lease machineries, Vehicles and excavation equipments
28 Deployment of labourers across site
29 Breakdown debris into smaller pieces
30 Response based clean up - save human lives
31 Prioritize the cleaning on the basis of Population density, Schools, nursing, Environmental impact
32 Segregate the waste into recyclable, non- recyclable, electronic waste and company assests
33 Send Recyclable waste to identified recycling facilities
34 Send non-recyclable waste to temporary dumping grounds
35 Send electronic waste to elctronic recycling facilities
36 Distribute assets to their respective firms
37 Setup weekly meetings with the supervisors to discuss on the challenges
38 Ensure the workers' fundamental requirements are met
39 Handle Media and Public relations
40 Provide daily status updates on the progress
41 Finalize cleanup and restoration of the services

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!