Question: This is an academic assignment. The problem statement is as follows: In the aftermath of September 11, 2001, terrorist attacks on the World Trade Center,

This is an academic assignment.

The problem statement is as follows:

In the aftermath of September 11, 2001, terrorist attacks on the World Trade Center, the New York City Department of Design and Construction was put in charge of recovery and clean-up operations at the site. The attack killed 2,823 people, destroyed a total of 8 buildings, and crushed 1,300 feet of the subway tunnel. Ultimately, the clean-up operations involved four construction firms, 3,000 workers, and 3.1 million man-hours. It took more than 100,000 truckloads to carry the 1.8 million tons of debris from the site. Amazingly, no workers were killed or critically injured during the clean-up effort, which officially ended on May 30, 2002, at a cost of $650 million. (Source: www.pbs.org/americarebuilds) Obviously, a project of this magnitude could not be completed successfully without careful planning and coordination of many, many activities. Indeed, many clean-up activities could be considered subprojects of the entire clean-up operation. Imagine that you were the person in charge of the clean-up operations at the World Trade Center site. No one has ever faced this task before, so no one can give you a nice, neat list of things to do with precise time estimates for each activity. It is an enormous task requiring careful consideration of human emotion, dignity, and safety concerns in addition to the monumental logistics and financial issues. And the world is watching all you do.

The demands of the issue are as follows:

Identify the key top-level activities you think would go into the clean-up project and prepare an AON project network summarizing the precedence relations among these activities. Also, describe how you would go about estimating the activity times and financial costs associated with these activities.

Description: Identification is done. Ask you to prepare an AON project network summarizing the precedence relations among these activities.

A Secure the parmeter
B Engage Stakeholders
C Setup High level teams/ Appoint a person to address media queries
D setup a Temporary office on site
E Get access to the blueprint of the buildings and the subway
F Inspection of affected areas
G Split the affected areas into sector/grids
H Identify the pathways for emergency services
I Set up access routes to hospitals, trauma centers, and critical care units
J set-up Communication towers
K Air surviellance and Monitoring
Identify routes for debris collection
L Restore electricity, water supply and drainage system of the affected area
M Liase with construction and transport companies
N Hire Site workers
O Lease machineries, Vehicles and excavation equipments
P Deployement of labourers across site
R Breakdown debris into smaller pieces
S Response based clean up - save human lives
T Prioritize the cleaning on the basis of Population density, Schools, nursing, Environmental impact
U Segregate the waste into recyclable and non- recyclable
V Identify the landfill and recycling facilities
W Identify temporary dumping grounds
X Handle Media and Public relations
Y Provide daily status updates on the progress

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!