Question: This is an individual exercise. Using Microsoft Project as the software tool, create PERT and GANTT charts for the following tasks. The most likely durations

This is an individual exercise. Using Microsoft Project as the software tool, create PERT and GANTT charts for the following tasks. The most likely durations have already been calculated for you. Next Wednesday is the project start date. Questions 1) What is the most likely date by which the project can be completed? 2) What tasks form the critical path for the project? 3) Management has decided to use Oracle as the database engine instead of Microsoft Access. This will add five days to the Database Design task for training and familiarization of the new tool. How does this affect the critical path and projected completion date? Why is there only one day delay in the project completion