Question: This is for my engineering econ class, can you explain how to do this step by step, thank you! 1. Draw an Activity on the

This is for my engineering econ class, can you explain how to do this step by step, thank you!This is for my engineering econ class, can you

1. Draw an Activity on the Node diagram and use the CPM method to determine the following: a. Total project time? b. Activities on the critical path? c. Amount of slack for each activity? (20 points) Activity Predecessor Duration (Days) A 4 B 5 A,B 6 D A,B 7 E C,D 4 F E 6 G E 7 H E 4 I GH 3 J GI 4 K F, J 5