Question: This is last DIY exercise in the semester. It covers material discussed this week on Monday - Project management. The task is following. Do readings

This is last DIY exercise in the semester. It covers material discussed this week on Monday - Project management.
The task is following.
Do readings (ch.8) assigned for this week if you have not done yet.
The following problem is similar to that one we solved in class (see readings).
Use data for the following project:
Activity Duration, weeks Predecessor
A Design/Funding 8
B Allocate/Renovate Office Space 12 A
C Order Servers and Network Switches 8 A
D Build Network 12 B,C
E Order Software 4 B,C
F Setup Firewall 4 E
G Test network under full load 8 F,D
1. Create Gantt chart for the schedule;
2. Identify Critical time and time Critical Path ;
3. Construct / draw AOA network.
4 Construct and draw AoN network with earliest/latest times of start/end.
Upload Excel File with the solved problem.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!