Question: This is project management course question from BUS 3 5 3 , SUSS As the project progresses, the following issues are encountered: i . The
This is project management course question from BUS SUSS
As the project progresses, the following issues are encountered:
i The raise floor Activity requirement is different from the initial design due to lack of the detailed floor plan. Additional work and different materials are required. Two additional days and an additional amount of $ are required. As it is an oversight of MOD, USB will not pay for this additional cost.
ii Due to the appreciation of Japanese Yen, the Supervise subcontractor on supply and install airconActivity costs more.
iii. USB has just purchased a new bank equipment which needs customisation. The duration of Customise banking equipmentActivity has to be increased by three days.
This requirement was not stated in the contract. USB agreed to pay for the additional work, but need the branch hand over date to remain on September You need to increase Activity s duration by days and request Mary to work on weekday, Saturday andor Sunday when necessary to meet the deadline. Mary agreed despite her disappointment. Make a decision on the dates.
Since the equipment causing the change is not in the contract, the cost will be charged separately to USB. MOD management wants the Cost Performance Index CPI to be based on the baselined cost. Hence, leave the Activity cost unchanged.
For the activities that has additional days, do I set them as "increse work but keep hours reseource work per day units the same or decrease the hour resources work per day units but keep the same amount of work?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock