Question: This is the conversion of the project work breakdown structure into an operating timetable. Oa, Chart Ob. Application Oc. Crash Od. Schedule Question 2 Not


























This is the conversion of the project work breakdown structure into an operating timetable. Oa, Chart Ob. Application Oc. Crash Od. Schedule Question 2 Not yet answered Points out of 1.00 F Flag question The basic approach ofall scheduling techniques is to form a network of activity and event relationships that graphically portrays the sequential relations between what in a project? Oa. Activities Ob. Nodes Oc. Events Od. Tasks All of the following are possible conditions for an activity except which one? Oa, it may have a successos) but no predecessos) Ob. It may have a predecessor(s) but no successor(s) Oc. It may have both predecessor(s) and successor(s) Od. It may not have a predecessor(s) or a successor(s) Question 4 Not yet answered Points out of1.00 v? Flag question These have a weakness of being difficult to follow when multiple paths exist, but these are more helpful in the handson task of managing the project. Oa. Networks, Gantt charts Ob. Activity sets, networks Oc. Gantt charts, networks Od. Gantt charts, activity sets Question 5 Not yet answered Points out of1.00 if\" Flag question The shortest time in which the entire network can be completed is referred to as the what? Oa. Critical time of the network Ob. Real duration of the network Oc. Elapsed time of the network Od. Slack time of the network Question 6 Not yet answered Points out of 1.00 'l' Flag question Project completion probabilities computed using just the critical path are always what? Oa. Optimistic Ob. Correct Oc. Pessimistic Od. Based on a 99 percent probability Question '7 Not yet answered Points out of 'I .00 'l' Flag question Activity 11 cannot be completed before 7 days since the start of Activity 10" is which type of restriction? Oa. Finish to Start Ob. Start to Start Oc. Finish to Finish Od. Startto Finish Question 8 Not yet answered Points out of 'I .00 t7 Flag question This is one possible way to check the nature and impacts of interactions between probabilistic paths in a network. Oa. Simulation Ob. Extrapolation Oc. Guessing Od. Probabilistic time estimates Question 9 Not yet answered Points out of1.00 tr Flag question On method of managing the uncertainty is to perform what on the data involved in our managerial decisions? Oa. Simulation Ob. Probability analysis Oc. Critical path analysis Od. Risk analysis Question 10 Not yet answered Points out of 1.00 Flag question Which of the following is not a software tool commonly used to manage projects, especially in relation to time and cost budgets? Oa. Microsoft Project Ob. Microsoft Excel Oc. Crystal Ball Od. Microsoft WordQuestion 11 Not yet answered Points out of 1.00 r; Flag question The formula for computing the costXtime slope for each activity that can be crashed is which of the following? Oa. (Crash cost + normal cost) I (crash time + normal time) Oh. (Crash cost normal cost) I (crash time - normal time} Oc. (Normal cost + crash cost) / (normal time + crash time} Go. (Normal cost crash cost) / (normal time crash time} Question 12 Not yet answered Points out of 1.00 'i' Flag question The two principles to follow when crashing a project focuses on the what? Oa. Critical path and selects the least expensive alternative Ob. Critical path and selects the most expensive alternative Oc. Shortest path and selects the least expensive alternative Od. Critical path and selects the most expensive alternative Question 13 Not yet answered Points out of 1.00 i' Flag question The points between the extreme points of the relationship between time use and resource use represent what? Oa. Time constrained projects 0 b. Resou rce constrained projects Oc. Alternative tradeoffs between time and resources Do. A nonfeasible solution space of tradeoff alternatives related to time and resource use Question 14 Not yet answered Points out of 1.00 V? Flag question This describes the amounts of individual resources an existing schedule requires during specific time periods. Oa. Resource loading Ob. Resource leveling Oc. Scope loading Od. Resource succeeding Question 15 Not yet answered Points out of1.00 l' Flag question This aims to minimize the periodby-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage. Oa. Resource loading Ob. Resource leveling Oc. Scope loading Od. Resource succeeding Question 16 Not yet answered Points out of 1.00 'f' Flag question A good ruleofthumb is not to schedule a scarce resource for more than what percentage of capacity? Oa. 7075 percent Ob. 7580 percent Oc. 8085 percent Od. 8590 percent Question 1'7 Not yet answered Points out of 'I .00 it? Flag question The usual purpose of this scheduling heuristic is to delay cash outflows as long as possible. Oa. Minimum slack first Ob. Shortest task first Oc. Most successors Od. As late as possible Question 18 Not yet answered Points out of 1.00 V Flag question Using this priority rule, activities are ordered by use of a specific resource, with the largest user heading the list. Oa. As Soon As Possible Ob. As Late As Possible Oc. Shortest Task First Od. Most Resources First Question 19 Not yet answered Points out of 1.00 F Flag question Priorities are assigned to activities according to some rule not associated with task length, slack, or resource requirements. Oa. Minimum Slack First Ob. Most Critical Followers 0:. Most Successors 0 d. Arbitrary Question 20 Not yet answered Points out of l .00 X\" Flag question One ofthe problems that Goldratt observed was that ifan activity has slack time, the task might become delayed until the slack is removed. This is referred to as what? Oa. Goldratt's Law Ob. Murphy's Law 0c. The delay game Go. The student syndrome Question 21 Not yet answered Points out of 1.00 P Flag question Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage, in-process inventory, and what? a. Resource utilization Ob. Time utilization Oc. Management delay Od. Schedule utilization
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
