Question: This is the schedule compression method where you add resources to shorten or accelerate schedule duration: Normal Fast Tracking Resource Clashing Resource Acceleration Crashing

This is the schedule compression method where you add resources to shorten or accelerate schedule duration:
Normal
Fast Tracking
Resource Clashing
Resource Acceleration
Crashing