Question: 1 is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. Select one: a . Parametric estimating b .
is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
Select one:
a Parametric estimating
b Analogous estimating
c Earned Value Management
d BottomUp estimating
The key benefit of the process is that it generates planned dates for completing project activities.
Select one:
a Define Activities
b Develop Schedule
c Control Schedule
d Estimate Activity Resources
is a schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources.
Select one:
a Crashing
b Fast Tracking