Question: This is under a project management course. A project with below network diagram and crashing information are given. As a project manager: 1. Which activity

This is under a project management course.
A project with below network diagram and crashing information are given. As a project manager: 1. Which activity do you choose for crashing? Explain why? (6 p) 2. Explain how best you spend 700$ to crash the project? (2 p) Fill in your answer here