Question: Time in Workdays Activity Optimistic Most Likely Pessimistic A 4 7 10 B 2 4 8 C 2 5 8 D 16 19 28 E
Time in Workdays
| Activity | Optimistic | Most Likely | Pessimistic |
| A | 4 | 7 | 10 |
| B | 2 | 4 | 8 |
| C | 2 | 5 | 8 |
| D | 16 | 19 | 28 |
| E | 6 | 9 | 24 |
| F | 1 | 7 | 13 |
| G | 4 | 10 | 28 |
| H | 2 | 5 | 14 |
| I | 5 | 8 | 17 |
| J | 2 | 5 | 8 |
| K | 17 | 29 | 45 |
- Draw a project network diagram from the information given, showing the ES, EF, LS, LF times.
- Which is the critical path?
- How long will it take to complete the project?
- What are the respective floats on activities D & I?
- According to this baseline schedule what are the latest start dates for activities E and K?
- What is the impact on project duration if activity D takes three days longer than planned?
- If the average duration for sourcing capital projects is 70 days, what is likelihood that this project will be completed on time?
Consider the following data for activities in a hypothetical project:
|
Activity |
Predecessor | Estimated time in weeks | ||
| o | m | p | ||
| A | - | 1 | 2 | 5 |
| B | - | 1 | 2 | 6 |
| C | - | 3 | 4 | 7 |
| D | - | 4 | 8 | 13 |
| E | A, F | 2 | 3 | 4 |
| F | B | 3 | 4 | 5 |
| G | C, D, E | 2 | 3 | 5 |
| H | D, G | 1 | 2 | 5 |
| I | E | 2 | 7 | 15 |
| J | G | 6 | 8 | 9 |
| K | J, I | 1 | 2 | 4 |
| L | H | 2 | 3 | 8 |
Required
- Draw and label the network diagram.
- Determine the critical path.
- What is the probability of completing this project in 21 weeks?