Question: Time in Workdays Activity Optimistic Most Likely Pessimistic A 4 7 10 B 2 4 8 C 2 5 8 D 16 19 28 E

Time in Workdays

Activity

Optimistic

Most Likely

Pessimistic

A

4

7

10

B

2

4

8

C

2

5

8

D

16

19

28

E

6

9

24

F

1

7

13

G

4

10

28

H

2

5

14

I

5

8

17

J

2

5

8

K

17

29

45

  1. Draw a project network diagram from the information given, showing the ES, EF, LS, LF times.
  2. Which is the critical path?
  3. How long will it take to complete the project?
  4. What are the respective floats on activities D & I?
  5. According to this baseline schedule what are the latest start dates for activities E and K?
  6. What is the impact on project duration if activity D takes three days longer than planned?
  7. If the average duration for sourcing capital projects is 70 days, what is likelihood that this project will be completed on time?

Consider the following data for activities in a hypothetical project:

Activity

Predecessor

Estimated time in weeks

o

m

p

A

-

1

2

5

B

-

1

2

6

C

-

3

4

7

D

-

4

8

13

E

A, F

2

3

4

F

B

3

4

5

G

C, D, E

2

3

5

H

D, G

1

2

5

I

E

2

7

15

J

G

6

8

9

K

J, I

1

2

4

L

H

2

3

8

Required

  1. Draw and label the network diagram.
  2. Determine the critical path.
  3. What is the probability of completing this project in 21 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!