Question: this need to be turn into a Network Diagram Activity ID Activity Name Duration Successors A1000 Building Permit (Milestone) 0 A1010 A1010 Soil Erosion Protection
this need to be turn into a Network Diagram
| Activity ID | Activity Name | Duration | Successors |
| A1000 | Building Permit (Milestone) | 0 | A1010 |
| A1010 | Soil Erosion Protection | 2 | A1020 |
| A1020 | Clear Site | 2 | A1030 |
| A1030 | Building Pad Layout | 1 | A1040 |
| A1040 | F.R.P. Slab on Grade | 3 | A1050 |
| A1050 | Frame 1st Flr. Walls | 1 | A1060 |
| A1060 | Frame Ceiling Joists | 1 | A1070 |
| A1070 | 2nd Flr. Subfloor | 1 | A1080 |
| A1080 | Frame 2nd Flr. Walls | 1 | A1090, A1180 |
| A1090 | Frame 2nd Flr. Ceiling Joists | 1 | A1100, A1110 |
| A1100 | Frame Rafters/Fascia | 3 | A1120 |
| A1110 | Wall Sheathing | 3 | A1150 |
| A1120 | Roof Sheathing | 2 | A1130 |
| A1130 | Roof Felt/Shingles | 2 | A1140, A1190 |
| A1140 | Metal Trim | 1 | A1280 |
| A1150 | House Wrap | 1 | A1160 |
| A1160 | Doors/Windows | 1 | A1170 |
| A1170 | Nichiha Siding | 3 | A1280 |
| A1180 | Frame Stairs/Handrail | 2 | A1190 |
| A1190 | Rough HVAC | 2 | A1200 & A1210(SS w/1 day lag), A1230 |
| A1200 | Rough Electrical | 2 | A1220 |
| A1210 | Rough Plumbing | 1 | A1220 |
| A1220 | 2nd Flr. Insulation | 2 | A1230 |
| A1230 | 2nd Flr. Drywall | 4 | A1240 |
| A1240 | 2nd Flr. Paint | 2 | A1250 |
| A1250 | Finish HVAC | 2 | A1260 & A1270(SS w/1 day lag), A1300 |
| A1260 | Finish Electrical | 1 | A1300 |
| A1270 | Finish Plumbing | 2 | A1300 |
| A1280 | Exterior Paint | 2 | A1290 |
| A1290 | Landscaping | 2 | A1300 |
| A1300 | Punchlist | 2 | end of project |