Question: This Question: 1 pt Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Time Activity

This Question: 1 pt Task time estimates for the
This Question: 1 pt Task time estimates for the
This Question: 1 pt Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Time Activity (in hours) Immediate Predecessor(s) 6.0 B 75 5.0 8.0 B,C E 48 B,C F 7.7 D G 5.0 E, F This exercise contains only part a. a) The correct precedence diagram for the project is shown in a Figure 1 . E F B Figure 2 . . Figure 3 E