A Company wants to execute a project within 95 weeks. This project includes 10 activities (labeled A, B, ...,J), where their precedence relationships are shown in the following table: Activity Predecessor Activity Normal Crash Time(weeks) Time(weeks) 32 28 Normal Cost (in million $) Crash Cost (in million $) A 160 180 B 28 25 146 125 170 C A 36 31 210 D B 16 13 60 72 E B 32 27 135 160 F B 54 47 215 257 G D 17 15 90 96 H 17 120 E,G E,G F,C 20 34 132 226 I 30 190 J 18 16 80 84 a) Draw the project network according to the previous table. (b)Find all possible paths and the corresponding lengths to finish the project. (c) Which is the critical path and what is its length? (d) Determine the least expensive way to crash activities to reduce overall duration to 95 weeks using Marginal cost analysis

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!