Question: This question is based on Project Management Remove Old Wallpaper Patch Walls Put Up New Wallpaper 31 3 2 5 Is this project technically constrained

This question is based on Project Management This question is based on Project Management
Remove Old Wallpaper Patch Walls Put Up New Wallpaper 31 3 2 5 Is this project technically constrained or resources constrained? Explain why by defining technically and resource constrained and how this network diagram support your