Question: This question is based on the following linear programming problem, which has been written to plan the production of two products. The company wants to

This question isbased on the following linear programming problem, which has been written to plan the production of two products. The company wants to maximize its profits.
X1= number of product 1 produced in each batch
X2= number of product 2 produced in each batch
MAX: 150 X1+250 X2
Subject to: 2 X1+5 X2<=200
3 X1+7 X2<=175
X1, X2>=0
How many units of resource 1 are consumed by each unit of product 1 produced?
Question 4 options:
a)
2
b)
3
c)
1
d)
5