Question: This question is from my Production Management class. Please solve it with an appropriate explanation. Find the MAD, MSE, and MAPE for F1 and F2,

This question is from my Production Management class. Please solve it with an appropriate explanation.This question is from my Production Management

Find the MAD, MSE, and MAPE for F1 and F2, round to 2 decimals. Predicted Demand Predicted Demand Period Demand F1 F2 1 68 66 66 2 75 68 3 68 72 70 70 4 74 71 72 5 69 72 74 6 72 70 76 7 80 71 78 8 78 74 80