Question: THIS QUESTION PROJECT MANAGEMENT QUESTION . According to the table given below, Activity A B C D E F G H J K L M
THIS QUESTION PROJECT MANAGEMENT QUESTION
. According to the table given below,
| Activity | A | B | C | D | E | F | G | H | J | K | L | M |
| Duration | 6 | 1 | 2 | 4 | 1 | 1 | 6 | 4 | 4 | 3 | 5 | 3 |
| priority | -- | -- | A, B | -- | C, D | E | E | F | F | G, H | J, K | L |
| Activities |
a. Calculate the critical path and Project completion time. b. Calculate the slack times for the activities. c. By performing the resource load on the table given below, Do resource leveling on activities. (Activities over 8 hours per day) will be evaluated. The maximum time that can be spent per day is 16 hours.)