Question: This subject is Management Science EOQ QUESTION Calculate the Total annual cost D=1,500units Q*=250units S=$10per order N=5 orders per year H=$.50 per unit per year
This subject is Management Science
EOQ QUESTION
Calculate the Total annual cost D=1,500units Q*=250units S=$10per order N=5 orders per year H=$.50 per unit per year T= 50 days.
1. Using a= 0.4,determine the forecast for the next period if the value forecasted for the past period was 41,758 and the actual demand turned out to be 42,555.