Question: * This table provides information for the next two MCQs and Problem 2. Pessimistic 0 4 8 9 Activity Immediate Optimistic Most Predecessor Likely 2

* This table provides information for the next two MCQs and Problem 2. Pessimistic 0 4 8 9 Activity Immediate Optimistic Most Predecessor Likely 2 3 B 2 5 A 1 2 D A 5 5 E BC 6 7 B 14 14 G D, E 1 5 1 GF 4 Which activities are part of the critical path? 3 8 14 9 8 0.333 1000 1330 0.000 0.333 0.000 11333 1.167 0.111 1.000 1.780 0.000 0.111 0.000 1.780 1 362 A-B-E-G-H A-C-E-G-H A-D-G-H B-F-H None of the above
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
