This table will cover information for Q1-Q3
| year | project A | project B |
| 0 | -1000 | -900 |
| 1 | 300 | 240 |
| 2 | 300 | 240 |
| 3 | 300 | 240 |
| 4 | 300 | 240 |
| 5 | 300 | 240 |
For above project, interest rate is 10%
Q1 what is NPV of project A
2) q2 what is IRR of project b
3) NPV for A is higher than NPV for project B
True
False