Question: This value tells the project manager the forecasted cost variance (CV) at the completion of the project. Question 89 options: AVC VAC CAV CVA
This value tells the project manager the forecasted cost variance (CV) at the completion of the project. Question 89 options:
AVC
VAC
CAV
CVA