Question: Thompson Construction began a construction project in 2016. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the

Thompson Construction began a construction project in 2016. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows:

201620172018
Costs incurred during the year$250,000$600,000$190,000
Estimated costs to complete750,000212,500-0-
Partial Billings375,000500,000375,000
Collections187,500469,000593,500


Instructions: Assuming Thompson satisfies its performance obligation over time:

1.) Prepare a schedule that computes the gross profit for 2016 - 2018.

2.) Determine balance of Construction in Progress at the end of 2016

3.) Determine the net amount for construction in progress inventory should be reported on the 2017 balance sheet.

Step by Step Solution

3.52 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Calculation of Gross Profit Particulars 2016 Calculation Working Amount 2016 Turnover Sale Given 3... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

60bdf2ae84972_214259.pdf

180 KBs PDF File

Word file Icon

60bdf2ae84972_214259.docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!