Thompson Construction began a construction project in 2016. The contract price was $1,250,000, and the estimated costs
Fantastic news! We've Found the answer you've been seeking!
Question:
Thompson Construction began a construction project in 2016. The contract price was $1,250,000, and the estimated costs were $1,000,000. Data for each year of the contract are as follows:
2016 | 2017 | 2018 | |
Costs incurred during the year | $250,000 | $600,000 | $190,000 |
Estimated costs to complete | 750,000 | 212,500 | -0- |
Partial Billings | 375,000 | 500,000 | 375,000 |
Collections | 187,500 | 469,000 | 593,500 |
Instructions: Assuming Thompson satisfies its performance obligation over time:
1.) Prepare a schedule that computes the gross profit for 2016 - 2018.
2.) Determine balance of Construction in Progress at the end of 2016
3.) Determine the net amount for construction in progress inventory should be reported on the 2017 balance sheet.