Question: Thrasher Construction Co. was contracted to construct a building for $1,075,000. The building is owned by the customer throughout the contract period. The contract provides





Thrasher Construction Co. was contracted to construct a building for $1,075,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher's accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: 20X5Construction costs incurred during the year, $198,000; estimated costs to complete, $693,000; progress billings during the year, $168,000, and collections, $154,000. 20X6Construction costs incurred during the year, $495,000; estimated costs to complete, $209,000; progress billing during the year, $420,500; and collections, $418,000. 20X7 Construction costs incurred during the year, $215,000. Because the contract was completed, the remaining balance was billed and later collected in full per the contract. 3-a. Now assume that the building is owned by Thrasher throughout the construction period and title is transferred to the customer only once the building is fully constructed. Prepare the journal entries required to record the events from 20x5 to 20X7. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.) View transaction list Journal entry worksheet
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
