Question: Three activities are candidates for crashing on a project network for a large computer installation ( all are, of course, critical ) . Activity details

Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table:
\table[[Activity,\table[[Normal],[Time (days)]],\table[[Crash],[Time (days)]],\table[[Normal],[Cost]],\table[[Total Cost],[with],[Crashing]],Immediate Predecessor(s)],[A,7,6,$5,000,$5,600,-],[B,4,2,$1,200,$3,100,A],[C,11,9,$4,600,$6,600,B]]
a) Activity that should be crashed first to reduce the project duration by 1 day is
b) Activity that should be crashed next to reduce the project duration by one additional day is
c) Total cost of crashing the project by 2 days =$3100.(Enter your response as an integer.)
 Three activities are candidates for crashing on a project network for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!