Question: Three activities are candidates for crashing on a project network for a large computer installation ( all are, of course, critical ) . Activity details
Three activities are candidates for crashing on a project network for a large computer installation all are, of course, critical Activity details are in the following table:
tableActivitytableNormalTime daystableCrashTime daystableNormalCosttableTotal CostwithCrashingImmediate PredecessorsA$$B$$AC$$B
a Activity that should be crashed first to reduce the project duration by day is
b Activity that should be crashed next to reduce the project duration by one additional day is
c Total cost of crashing the project by days $Enter your response as an integer.