Question: Three teams ( T 1 , T 2 , and T 3 ) work in the process depicted in the Figure below, where the numbers

Three teams (T1, T2, and T3) work in the process depicted in the Figure below, where
the numbers in each activity indicate processing times in minutes.
There are three staff members in T1, two in T2, and five in T3.
Calculate the capacity utilisation of the process assuming that the actual
throughput is 4 jobs/h.Three teams (T1, T2, and T3) work in the process depicted in the Figure below, where
the numbers in each activity indicate processing times in minutes.
There are three staff members in T1, two in T2, and five in T3.
Calculate the capacity utilisation of the process assuming that the actual
throughput is 4 jobs/h.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!