Question: Three work stations in an assembly line require various operational times with corresponding probabilities. Time in Minutes Station One Station 2 Station 3 4 .25
Three work stations in an assembly line require various operational times with corresponding probabilities.
| Time in Minutes | Station One | Station 2 | Station 3 |
| 4 | .25 | .10 | .05 |
| 5 | .25 | .30 | .25 |
| 6 | .25 | .40 | .25 |
| 7 | .25 | .20 | .45 |
Simulate the flow of 10 motors through the assembly line. Make the assumption that if a unit is completed for e.g. at station 1 while station 2 is busy, the operator at station 1 will be forced to wait (blocking). When station 2 is free to work on the output from station 1, then station 1 can proceed to work on the next unit. Simulate to derive average output rate of the line.
Use the following random numbers 62890 25703 30835 24684 09735 2569 027834 45792 31585 81820