Question: Throughput Management at Lantana Inc. has decided to begin using throughput as a divisional performance measure. The Carolina Division is a job shop that carefully

Throughput
Management at Lantana Inc. has decided to begin using throughput as a divisional performance measure. The Carolina Division is a job shop that carefully crafts furniture to customer specifications. The following first quarter information is available for the division:
Good units started, completed, and sold98,400Total units completed229,900Total value-added hours of processing time15,160Total hours of divisional time55,000
a. What is the divisions manufacturing cycle efficiency?
Note: Round percentage to one decimal point (i.e. round 4.555% to 4.6%).
Answer 1%
b. What is the divisions process productivity?
Note: Round amount to one decimal point (i.e. round 4.555 to 4.6).
Answer 2 units per hour
c. What is the divisions process quality yield?
Note: Round percentage to one decimal point (i.e. round 4.555% to 4.6%).
Answer 3%
d. What is the total hourly throughput?
Note: Round amount to one decimal point (i.e. round 4.555 to 4.6).
Answer 4 units per hour

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!