Question: Tiles ( 1 5 ' ' by 8 ' ' ) can be installed at a rate of 5 0 per worker hour. The floor
Tiles by can be installed at a rate of per worker hour. The floor of a large lobby area by :
to be covered with these tiles. If twelve workers are assigned to this task, what duration to the nearest whole
should be assigned to this activity?