Question: Time 0 Time 1 Time 2 Time 3 Project A -10,000 5 ,000 4 ,000 3 ,000 Project B - 10,000 4,000 3,000 10,000 -
Time 0 Time 1 Time 2 Time 3 Project A -10,000 5 ,000 4 ,000 3 ,000 Project B - 10,000 4,000 3,000 10,000 - 22 If Wise Guy Inc is choosing one of the above of 7%, which should the company choose? usive projects (Project A or Project B), given a discount rate M O A. Project B O B. Project A OC. Neither project - both have negative NPV. OD. Both projects - both have positive NPV