Question: Time and material contracts are used on projects _ _ _ _ _ . Question 2 8 options: for work that is greater in scope

Time and material contracts are used on projects _____.
Question 28 options:
for work that is greater in scope
for work that has no uncertainty
where the project rather than the contractor assumes the risk
where the fee is typically a percent of the fixed cost
where time is usually contracted on a day rate basis