Question: time and the critical path should also be determined. Here are the activity times: table [ [ Activity , Time ( weeks ) Immediate

time and the critical path should also be determined. Here are the activity times:
\table[[Activity,Time (weeks) Immediate Predecessor(s),Activity,Time (weeks) Immediate Predecessor(s),,],[A,6,-,E,4,B],[B,6,-,F,6,B],[C,3,A,G,11,C, E],[D,2,A,H,6,D , F]]
Dave's earliest start (ES) and earliest finish (EF) are:
\table[[Activity,ES,EF],[A,0,6],[B,0,6],[C,6,9],[D,6,8],[E,6,10]]