Question: TIME (DAYS) INDEDIATE PREDECESSORS ACTIVITY d has ps in 3 6 8 net- B 2 4 4 1 2 3 D 6 7 8 C

TIME (DAYS) INDEDIATE PREDECESSORS ACTIVITY d has ps in 3 6 8 net- B 2 4 4 1 2 3 D 6 7 8 C 2 E 4 6 STIC BD F 10 14 G 1 2. 4 LE H 3 6 9 191 1 10 11 12 G 1 14 16 20 C K 2 8 10 H a) Determine the expected completion time and variance for each activity b) Determine the total project completion time and the critical path for the project c) Determine ES. EF. LS LF and slack for each activity d) What is the probability that Kelle Carpet and Tom will finish the project in 40 days or less
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
