Question: TIME (DAYS) INDEDIATE PREDECESSORS ACTIVITY d has ps in 3 6 8 net- B 2 4 4 1 2 3 D 6 7 8 C

TIME (DAYS) INDEDIATE PREDECESSORS ACTIVITY d has

TIME (DAYS) INDEDIATE PREDECESSORS ACTIVITY d has ps in 3 6 8 net- B 2 4 4 1 2 3 D 6 7 8 C 2 E 4 6 STIC BD F 10 14 G 1 2. 4 LE H 3 6 9 191 1 10 11 12 G 1 14 16 20 C K 2 8 10 H a) Determine the expected completion time and variance for each activity b) Determine the total project completion time and the critical path for the project c) Determine ES. EF. LS LF and slack for each activity d) What is the probability that Kelle Carpet and Tom will finish the project in 40 days or less